# CodeMark evaluation and Product Quality Plan

CodeMark Australia | Worked example with fictional data

Step: Assemble test evidence and the Product Quality Plan
Owner: Engineering + factory quality + certification body
When: Before evaluation and factory review

## Gather first
- Agreed scope matrix
- Full lab reports
- Controlled drawings and specifications
- Factory process map
- Appendix 1 requirements

## How to prepare it
1. Map the bill of materials, installed configuration and production process to the tested sample and report. Get written decisions on variations and evidence gaps.
2. For each Appendix 1 requirement, name the procedure, person, frequency and evidence. Include incoming checks, manufacturing inspections, release, traceability, corrective action, complaints and recall.
3. Review records from one trial lot before submitting. Track each evaluation finding with the requested action, owner, due date and certifier confirmation.

## Example

### Incoming check
For fictional FP-12, receiving verifies the specified panel core against the approved bill of materials. The recorded lot links to its supplier evidence.

### Trace exercise
Quality starts with a dispatched serial or lot and retrieves the factory inspection, approved component batch and customer shipment.

### Finding example
Work instruction revision differs from the approved drawing. Engineering reconciles the revisions, trains the line lead and submits the new production record for closeout.

## Review
A reviewer can link the tested configuration to production controls and verify open and closed findings.

## Handoff
Give the certifier a dated copy. Keep the approved version accessible to production and field quality staff.

Official reference: CodeMark rules and Appendix 1
https://codemark.abcb.gov.au/sites/default/files/resources/2022/CodeMark-australia-scheme-rules-2016-2.pdf

Use the current rules and any prescribed forms for your engagement.