# CodeMark project acceptance record

CodeMark Australia | Worked example with fictional data

Step: Verify the certificate and approve project use
Owner: Procurement + designer + building surveyor
When: Before specifying, purchasing or substituting

## Gather first
- Current complete certificate and register entry
- Project drawings and specifications
- NCC edition and local variations
- Purchase order and installation instructions

## How to prepare it
1. Search the advertised certificate number in the JASANZ CodeMark register. Save the verification date, status, issuer and complete certificate version with any referenced instructions.
2. Compare the specified product, application and installation with each certificate condition. Check model, site use, construction and components against the actual order and design.
3. Assign the project designer and appropriate approval authority any scope gaps. Record their decision, additional evidence and site checks before accepting a substitution.

## Example

### Fictional substitution
FP-12’s installation drawing specifies one substrate. A contractor proposes a different substrate. Procurement pauses acceptance while the designer checks the certificate and confirms how the new design will be substantiated.

### Retained evidence
Current certificate and public register status, project drawing revision, marked comparison, approval decision and inspection evidence.

## Review
The acceptance decision identifies what the certificate covers and what evidence supports every difference.

## Handoff
Attach the approval to the procurement and construction records, then give Site Quality the conditions to verify.

Official reference: JASANZ CodeMark register access