See what controls your launch date
Start with a sample project. Change the estimates, add a setback and see which handoffs move the finish.
Simulate a setback
This task has no slack in the plan.
What controls the finish
Change the duration on any row. Tasks with no slack currently set the earliest finish.
Confirm intended use, predicate and pathway
Regulatory Affairs and Product
Dependencies and handoff
Waits for Project kickoff
Hand over Classification memo and a route decision supported by the device facts.
Day 0 to Day 14No slackApprove protocols and confirm lab access
Clinical, Engineering and Quality
Dependencies and handoff
Waits for Confirm intended use, predicate and pathway
Hand over Approved criteria, representative configuration and booked test facilities.
Day 14 to Day 38No slackPrepare risk file and labeling
Quality and Regulatory Affairs
Dependencies and handoff
Waits for Confirm intended use, predicate and pathway
Hand over Controlled claims, intended use, risk controls and draft labeling.
Day 14 to Day 4958 days slackExecute testing and review reports
Engineering and testing labs
Dependencies and handoff
Waits for Approve protocols and confirm lab access
Hand over Signed reports, approved deviations and traceability to claims and risks.
Day 38 to Day 107No slackCompile and submit eSTAR dossier
Regulatory Affairs
Dependencies and handoff
Waits for Execute testing and review reports · Prepare risk file and labeling
Hand over Validated package, accountable author and submission receipt.
Day 107 to Day 119No slackAllow for agency review and sponsor responses
FDA and Regulatory Affairs
Dependencies and handoff
Waits for Compile and submit eSTAR dossier
Hand over Official decision. The sample calendar allowance includes time for sponsor responses and holds.
Day 119 to Day 229No slack
View or copy the launch brief
FDA 510(k) launch plan FDA decision received · Day 229 · 229 days No target comparison Delay tested Execute testing and review reports · 14 days Effect on project finish 14 days Tasks with no available slack - Confirm intended use, predicate and pathway - Approve protocols and confirm lab access - Execute testing and review reports - Compile and submit eSTAR dossier - Allow for agency review and sponsor responses Schedule and handoffs Confirm intended use, predicate and pathway · Day 0 to Day 14 Regulatory Affairs and Product · 14 days duration · 0 days slack Can start at kickoff Classification memo and a route decision supported by the device facts. Approve protocols and confirm lab access · Day 14 to Day 38 Clinical, Engineering and Quality · 24 days duration · 0 days slack Waits for Confirm intended use, predicate and pathway Approved criteria, representative configuration and booked test facilities. Prepare risk file and labeling · Day 14 to Day 49 Quality and Regulatory Affairs · 35 days duration · 58 days slack Waits for Confirm intended use, predicate and pathway Controlled claims, intended use, risk controls and draft labeling. Execute testing and review reports · Day 38 to Day 107 Engineering and testing labs · 69 days duration · 0 days slack Waits for Approve protocols and confirm lab access Signed reports, approved deviations and traceability to claims and risks. Compile and submit eSTAR dossier · Day 107 to Day 119 Regulatory Affairs · 12 days duration · 0 days slack Waits for Execute testing and review reports, Prepare risk file and labeling Validated package, accountable author and submission receipt. Allow for agency review and sponsor responses · Day 119 to Day 229 FDA and Regulatory Affairs · 110 days duration · 0 days slack Waits for Compile and submit eSTAR dossier Official decision. The sample calendar allowance includes time for sponsor responses and holds. Assumptions The review row estimates calendar time from submission to decision, including time for sponsor responses and holds. FDA describes its review goal in FDA days, which exclude certain holds. Replace the sample with an estimate for your case. Calendar days with activities running in parallel where dependencies allow. Confirm actual dates with owners and outside reviewers.
How the dates are calculated
These estimates use calendar days. A task starts when all listed predecessors finish. The model assumes your team can staff parallel work. Confirm dates with task owners and external reviewers.
The review row estimates calendar time from submission to decision, including time for sponsor responses and holds. FDA describes its review goal in FDA days, which exclude certain holds. Replace the sample with an estimate for your case.
Open the FDA 510(k) guide