Coprsetr Lab
LAUNCH PLANNER

See what controls your launch date

Start with a sample project. Change the estimates, add a setback and see which handoffs move the finish.

FDA decision receivedDay 229229 days from kickoff
Without the simulated delayDay 215215 days from kickoff
Effect of this delay14 days laterSet a start and target date to compare

Simulate a setback

This task has no slack in the plan.

What controls the finish

Change the duration on any row. Tasks with no slack currently set the earliest finish.

  1. Confirm intended use, predicate and pathway

    Regulatory Affairs and Product

    Dependencies and handoff

    Waits for Project kickoff

    Hand over Classification memo and a route decision supported by the device facts.

    Day 0 to Day 14No slack
  2. Approve protocols and confirm lab access

    Clinical, Engineering and Quality

    Dependencies and handoff

    Waits for Confirm intended use, predicate and pathway

    Hand over Approved criteria, representative configuration and booked test facilities.

    Day 14 to Day 38No slack
  3. Prepare risk file and labeling

    Quality and Regulatory Affairs

    Dependencies and handoff

    Waits for Confirm intended use, predicate and pathway

    Hand over Controlled claims, intended use, risk controls and draft labeling.

    Day 14 to Day 4958 days slack
  4. Execute testing and review reports

    Engineering and testing labs

    Dependencies and handoff

    Waits for Approve protocols and confirm lab access

    Hand over Signed reports, approved deviations and traceability to claims and risks.

    Day 38 to Day 107No slack
  5. Compile and submit eSTAR dossier

    Regulatory Affairs

    Dependencies and handoff

    Waits for Execute testing and review reports · Prepare risk file and labeling

    Hand over Validated package, accountable author and submission receipt.

    Day 107 to Day 119No slack
  6. Allow for agency review and sponsor responses

    FDA and Regulatory Affairs

    Dependencies and handoff

    Waits for Compile and submit eSTAR dossier

    Hand over Official decision. The sample calendar allowance includes time for sponsor responses and holds.

    Day 119 to Day 229No slack
View or copy the launch brief
FDA 510(k) launch plan
FDA decision received · Day 229 · 229 days
No target comparison
Delay tested  Execute testing and review reports · 14 days
Effect on project finish  14 days

Tasks with no available slack
- Confirm intended use, predicate and pathway
- Approve protocols and confirm lab access
- Execute testing and review reports
- Compile and submit eSTAR dossier
- Allow for agency review and sponsor responses

Schedule and handoffs
Confirm intended use, predicate and pathway · Day 0 to Day 14
Regulatory Affairs and Product · 14 days duration · 0 days slack
Can start at kickoff
Classification memo and a route decision supported by the device facts.

Approve protocols and confirm lab access · Day 14 to Day 38
Clinical, Engineering and Quality · 24 days duration · 0 days slack
Waits for  Confirm intended use, predicate and pathway
Approved criteria, representative configuration and booked test facilities.

Prepare risk file and labeling · Day 14 to Day 49
Quality and Regulatory Affairs · 35 days duration · 58 days slack
Waits for  Confirm intended use, predicate and pathway
Controlled claims, intended use, risk controls and draft labeling.

Execute testing and review reports · Day 38 to Day 107
Engineering and testing labs · 69 days duration · 0 days slack
Waits for  Approve protocols and confirm lab access
Signed reports, approved deviations and traceability to claims and risks.

Compile and submit eSTAR dossier · Day 107 to Day 119
Regulatory Affairs · 12 days duration · 0 days slack
Waits for  Execute testing and review reports, Prepare risk file and labeling
Validated package, accountable author and submission receipt.

Allow for agency review and sponsor responses · Day 119 to Day 229
FDA and Regulatory Affairs · 110 days duration · 0 days slack
Waits for  Compile and submit eSTAR dossier
Official decision. The sample calendar allowance includes time for sponsor responses and holds.

Assumptions
The review row estimates calendar time from submission to decision, including time for sponsor responses and holds. FDA describes its review goal in FDA days, which exclude certain holds. Replace the sample with an estimate for your case.
Calendar days with activities running in parallel where dependencies allow. Confirm actual dates with owners and outside reviewers.

How the dates are calculated

These estimates use calendar days. A task starts when all listed predecessors finish. The model assumes your team can staff parallel work. Confirm dates with task owners and external reviewers.

The review row estimates calendar time from submission to decision, including time for sponsor responses and holds. FDA describes its review goal in FDA days, which exclude certain holds. Replace the sample with an estimate for your case.

Open the FDA 510(k) guide

Keyboard shortcuts

⌘K or /
Search everything
?
This list
g h
Home
g l
Guide library
g f
Find my path
g t
Templates
g p
Playbooks
g w
My workspace
g d
Deadline calendar
g c
Regulatory changes