See what controls your launch date
Start with a sample project. Change the estimates, add a setback and see which handoffs move the finish.
Simulate a setback
This task can take 13 days longer before the original finish moves.
What controls the finish
Change the duration on any row. Tasks with no slack currently set the earliest finish.
Agree the ISMS scope
ISMS lead and sponsor
Dependencies and handoff
Waits for Project kickoff
Hand over Approved boundary, sites, interfaces and obligations.
Day 0 to Day 12No slackTreat risks and prepare the SoA
ISMS lead and risk owners
Dependencies and handoff
Waits for Agree the ISMS scope
Hand over Risk treatment decisions, operating controls and a reconciled Statement of Applicability.
Day 12 to Day 441 day slackWait for certification audit availability
Project lead and certification body
Dependencies and handoff
Waits for Agree the ISMS scope
Hand over Dates for initial audit work and agreed scope.
Day 12 to Day 89No slackOperate controls and collect records
Service and control owners
Dependencies and handoff
Waits for Treat risks and prepare the SoA
Hand over Dated evidence and agreed security objective measures.
Day 44 to Day 741 day slackComplete internal audit and management review
Internal auditor and leadership
Dependencies and handoff
Waits for Operate controls and collect records
Hand over Audit findings, management decisions and assignments.
Day 74 to Day 881 day slackComplete Stage 1 and resolve readiness gaps
ISMS lead and certification body
Dependencies and handoff
Waits for Complete internal audit and management review · Wait for certification audit availability
Hand over Readiness review and agreed Stage 2 plan.
Day 89 to Day 101No slackComplete Stage 2 and respond to findings
Control owners and certification body
Dependencies and handoff
Waits for Complete Stage 1 and resolve readiness gaps
Hand over Stage 2 records and responses with supporting evidence.
Day 101 to Day 119No slackReceive certification decision
Certification body
Dependencies and handoff
Waits for Complete Stage 2 and respond to findings
Hand over Decision and certificate scope if certification is granted.
Day 119 to Day 127No slack
View or copy the launch brief
ISO 27001 launch plan Initial certification decision · Day 127 · 127 days No target comparison Delay tested Wait for certification audit availability · 14 days Effect on project finish 1 day Tasks with no available slack - Agree the ISMS scope - Wait for certification audit availability - Complete Stage 1 and resolve readiness gaps - Complete Stage 2 and respond to findings - Receive certification decision Schedule and handoffs Agree the ISMS scope · Day 0 to Day 12 ISMS lead and sponsor · 12 days duration · 0 days slack Can start at kickoff Approved boundary, sites, interfaces and obligations. Treat risks and prepare the SoA · Day 12 to Day 44 ISMS lead and risk owners · 32 days duration · 1 day slack Waits for Agree the ISMS scope Risk treatment decisions, operating controls and a reconciled Statement of Applicability. Wait for certification audit availability · Day 12 to Day 89 Project lead and certification body · 77 days duration · 0 days slack Waits for Agree the ISMS scope Dates for initial audit work and agreed scope. Operate controls and collect records · Day 44 to Day 74 Service and control owners · 30 days duration · 1 day slack Waits for Treat risks and prepare the SoA Dated evidence and agreed security objective measures. Complete internal audit and management review · Day 74 to Day 88 Internal auditor and leadership · 14 days duration · 1 day slack Waits for Operate controls and collect records Audit findings, management decisions and assignments. Complete Stage 1 and resolve readiness gaps · Day 89 to Day 101 ISMS lead and certification body · 12 days duration · 0 days slack Waits for Complete internal audit and management review, Wait for certification audit availability Readiness review and agreed Stage 2 plan. Complete Stage 2 and respond to findings · Day 101 to Day 119 Control owners and certification body · 18 days duration · 0 days slack Waits for Complete Stage 1 and resolve readiness gaps Stage 2 records and responses with supporting evidence. Receive certification decision · Day 119 to Day 127 Certification body · 8 days duration · 0 days slack Waits for Complete Stage 2 and respond to findings Decision and certificate scope if certification is granted. Assumptions Confirm audit availability, stage timing and finding closure expectations with the certification body. Internal audit and management review should reflect your actual scope and operating evidence. Calendar days with activities running in parallel where dependencies allow. Confirm actual dates with owners and outside reviewers.
How the dates are calculated
These estimates use calendar days. A task starts when all listed predecessors finish. The model assumes your team can staff parallel work. Confirm dates with task owners and external reviewers.
Confirm audit availability, stage timing and finding closure expectations with the certification body. Internal audit and management review should reflect your actual scope and operating evidence.