Implementation plan and responsibility record
DOE and NARUC DER Cybersecurity Baselines · Step 3 · Implement through operations and vendor agreements- Who prepares it
- Engineering + procurement + operations change owner
- When to prepare it
- Before changes and supplier renewals
Worked example
This example uses fictional details. Use the same fields with evidence from your work.
- Worked supplier handoff
- The aggregator maintains the service configuration backup. The utility provides a scheduled test window and signs off on restoration evidence. Both name an escalation contact.
Gather first
- Priority crosswalk
- Support agreements
- Safety procedures
- Change windows
- Acceptance checks
How to prepare it
- Assign a lead, system owner, supplier contact and reviewer. Write who operates each shared control and who reports failures.
- Set the planned change window and acceptance evidence. Define the condition for rolling back and who can make that decision.
- Review dependencies and safety constraints with operations. Save approval and arrange for a safe follow-up check.
Review
The implementation has approved roles, timing, acceptance criteria and a rollback decision owner.
Handoff
Pass the approved work to the change owner and independent reviewer.