COPRSETR WORKSHEET
Response decision and funded plan
DOE Electricity Cybersecurity RMP · Step 3 · Select and fund a response- Who prepares it
- Accountable risk owner + finance + procurement and operations
- When to prepare it
- At the decision gate and before the next change window
Worked example
This example uses fictional details. Use the same fields with evidence from your work.
- Worked decision
- Leadership funds a second communications path for the priority site. The owner agrees to test failover during an approved window and document restoration time against the business process recovery target.
Gather first
- Scenario register
- Risk tolerance
- Cost and staffing estimates
- Approved outage windows
- Supplier terms
How to prepare it
- Record two realistic response options where available, their estimated cost, expected risk reduction, dependencies and effect on operations.
- Name an owner, interim safeguard and measurable acceptance criterion. State the estimated remaining risk for each option.
- Obtain a funding or acceptance decision from the authorized owner. Record the date, review trigger and next milestone for reassessment.
Review
The decision has funding or explicit acceptance, and the team knows how it will prove completion.
Handoff
Send approved work to engineering and track it in the risk register.